The short answer
Laytime is the time the contract allows for loading or discharging a ship without extra payment. Demurrage is the agreed amount paid to the shipowner for each hour or day the ship is kept beyond that time. Both are set in the charter party between the shipowner and whoever hired the ship, and most oil sale contracts then pass the same cost on between seller and buyer.
The clock usually starts with a notice of readiness (NOR) from the ship's master, a few hours after the ship has arrived and is ready. It runs until loading or discharge is finished, minus the periods the contract says do not count. If the allowed time runs out, demurrage starts, and once a ship is on demurrage most interruptions no longer stop it.
For a buyer, three things matter more than the theory: who pays demurrage at each port under your SPA, which rules the laytime calculation follows, and how long you have to make or answer a claim. Get those in writing before you sign.
Two contracts, one waiting ship
Demurrage starts life in the charter party, the contract between the shipowner and the charterer. The charterer pays the owner if loading or discharge takes longer than the laytime. But in an oil deal the charterer is usually also a buyer or seller in a separate sale contract (SPA), and the delay is often caused by the other side of that sale: a slow loading terminal, a congested discharge port, a receiver whose tanks are not ready.
So most SPAs contain their own laytime and demurrage clause that moves the cost to whoever caused the delay. Which way it moves depends on the delivery term. Our Incoterms guide for oil cargoes explains the terms themselves; Incoterms says nothing about laytime or demurrage, so the SPA has to.
| Delivery term | Who normally charters the ship | Where the SPA demurrage clause bites |
|---|---|---|
| FOB load port | Buyer | Load port: the seller (whose terminal loads the ship) usually pays the buyer for delay beyond the allowed laytime |
| CFR / CIF discharge port | Seller | Discharge port: the buyer (whose port and tanks receive the cargo) usually pays the seller for delay beyond the allowed laytime |
| DES / DAP | Seller | Discharge port: same logic as CIF, with the seller carrying the voyage risk until delivery |
A published example: Equinor's (then Statoil's) conditions for FOB terminal crude sales, 1999 edition, give the seller 36 running hours to load, weather permitting, Sundays and holidays included, and make the seller pay the buyer demurrage for any excess time. That is one company's dated standard, not a market rule, but it shows the pattern: the party who controls the terminal carries the risk of the terminal being slow.
The words that decide the clock
Most of these terms have agreed meanings in BIMCO's Laytime Definitions for Charter Parties 2013, published by BIMCO together with other shipping bodies, including FONASBA, the shipbrokers' and agents' federation. They only apply if your contract incorporates them, so it is worth saying so.
| Term | What it means | Why a buyer should care |
|---|---|---|
| Laytime | The agreed time during which the owner keeps the ship available for loading or discharging without payment beyond the freight | This is your free time. Anything over it costs money |
| Running hours / running days | Hours or days that follow one after the other, day and night | Tanker forms such as ASBATANKVOY state laytime in running hours, so nights and weekends count unless excluded |
| SHINC / SHEX | Sundays and holidays included / excepted | SHEX stretches laytime over public holidays at the port |
| Weather working day | Time counts only while weather allows cargo work | Bad weather extends laytime instead of eating it |
| Notice of readiness (NOR) | Notice that the ship has arrived at the port or berth and is ready to load or discharge | Usually the trigger for the clock. An invalid NOR can mean laytime never started |
| WIBON / WIPON | Whether in berth or not / whether in port or not: NOR may be given from the usual waiting place, or from a recognised waiting place off the port | Moves the risk of a busy port onto the charterer, and through the SPA onto you |
| Reachable on arrival | The charterer promises an available berth the ship can reach safely without delay when it arrives | If you give this promise, waiting time for a berth is on you |
| Free pratique | The ship meets port health requirements | Often a condition for a valid NOR |
| Reversible laytime | The charterer may add load and discharge time together | Time saved at one end can be used at the other |
| Demurrage | An agreed amount paid to the owner for delay once laytime has expired, for which the owner is not responsible | The cost you are trying not to pay, or to pass on correctly |
| Despatch | An amount the owner pays if loading or discharge finishes early | The tanker clauses quoted in this guide do not provide for it, so check whether yours does |
One rule surprises most first-time buyers. BIMCO's definition says demurrage is not subject to the exceptions that apply to laytime unless the contract says so. People call it once on demurrage, always on demurrage: a weekend or a weather stop that would have paused laytime does not pause demurrage.
When the clock starts: notice of readiness and laycan
On the ASBATANKVOY tanker form, still widely used, the master gives NOR on arrival at the customary anchorage, "berth or no berth", and laytime starts six hours after the NOR is received, or when the ship is all fast in berth if that comes first. Sale contracts often reuse the same six-hour wording, as the two examples below show.
The sale contract then ties the NOR to the laycan or loading window. In the Equinor FOB example, a ship that gives NOR inside the window starts the clock six hours later or when it is moored, whichever is earlier. A ship that arrives early does not start the clock until 06:00 on the first day of the window, unless loading starts sooner. A ship that arrives late only starts the clock when loading begins. A gasoil sale considered by the English High Court in 2011 used the same three-way split for discharge into Ashkelon, with 48 hours of laytime, Sundays and holidays included.
A NOR is only valid if the ship really has arrived where the contract says and is ready, physically and legally. Under English law, a notice given before the ship is ready is invalid and does not become valid when the ship later becomes ready (The Mexico I). In The Tres Flores, pests in the holds made a NOR invalid until fumigation was done. Legal readiness usually means customs entry, immigration clearance and free pratique. Courts have also held that conduct can matter: where cargo work started without the charterer rejecting or reserving its position on a defective NOR, laytime has been treated as starting anyway (The Happy Day, 2002).
The practical point: if a ship arrives early, late, or tenders NOR from a place the contract does not allow, reply in writing at once, accepting the NOR or rejecting it with reasons. Silence is the expensive option.
What stops the clock, and what does not
Laytime is not simply arrival to departure. The contract lists periods that do not count. On ASBATANKVOY these include delay caused by the ship's own condition or breakdown, shifting from anchorage to berth, and discharging ballast or slops. The Equinor FOB terms add awaiting pilots, tugs or daylight, berthing delays from bad weather, tank cleaning and inspection, a ship that cannot meet the terminal's loading or deballasting rate, and any delay caused by the vessel, its owner or the buyer.
Some causes cut the rate instead of stopping the clock. ASBATANKVOY halves the demurrage rate when demurrage is caused by fire, explosion, storm, a strike, or a breakdown of machinery in or about the plant of the charterer, supplier, shipper or consignee. In Portolana v Vitol (2004), the Court of Appeal applied a version of that clause to a breakdown at the receiver's plant, and the owners got half demurrage for the whole disputed period. The Equinor FOB terms contain a similar half-rate rule for delays at the loading terminal.
Exceptions are read strictly against the party relying on them. If you want a delay excluded, name it. "Usual exceptions" invites an argument.
How long laytime is, and what the demurrage rate is, are agreed fixture by fixture. The ASBATANKVOY form leaves both blank for the parties to fill in. There is no single market number, and an offer that quotes one as standard should be read with care.
A simple laytime calculation, step by step
A laytime statement is just a timeline with deductions. This is an illustration with round hours, not a real voyage, and no money is involved; the rate is whatever your contract says.
- Allowed laytime. Say the SPA allows 36 running hours to discharge, Sundays and holidays included.
- Start. NOR is tendered at anchorage inside the delivery window. Under a six-hour clause, laytime starts six hours later, unless the ship is all fast in berth before then.
- Deductions. Shifting from anchorage to berth does not count. Neither does a stop while the ship repairs its own pump.
- End. The clock stops when hoses are disconnected, or whatever event the contract names.
- Result. Add up the counting hours. If they come to 50, the 14 hours over the 36 allowed are on demurrage, at the agreed hourly rate, pro rata for part hours.
- Half-rate periods. If part of those 14 hours was caused by a breakdown at the receiving terminal and the contract has a half-rate clause, that part is charged at half rate.
Every line of that statement comes from a document: the NOR, the statement of facts, the time sheets and the ship's logs. That is why the paperwork below matters so much.
The paperwork behind a demurrage claim, and the time limits
A demurrage claim normally rests on the NOR, the statement of facts (the port agent's record of arrival, berthing, hoses on and off and every stop), the time sheets, the ship's logs, pumping records and any letters of protest exchanged during the call. Bills of lading may be needed too.
Tanker charters usually set short deadlines. On BPVOY4, charterers are released from demurrage claims unless a written claim with all supporting documentation reaches them within 90 days of completion of discharge. In Kassiopi Maritime v FAL Shipping (2015), owners lost their whole claim because the port log and time sheets referred to in their letters of protest were not supplied. SHELLVOY 5 asks for notice within 60 days and the full claim within 90. The Equinor FOB sale terms give the buyer 90 days from the ship's sailing to get a demurrage claim to the seller.
Watch the gap between the two contracts. Demurrage specialists point out that a sale clause saying "demurrage as per charter party rate, terms and conditions" brings in the terms needed to calculate the claim, but not the charter party's time bar. If you want a deadline in your SPA, write one. Without any agreed deadline, English law falls back on the general six-year limit, and in Glencore v Sonol (2011) a seller's demurrage claim brought about six years after a 2005 gasoil discharge was held to be too late.
If you are the charterer, the owner's 90-day clock and your own SPA deadline may not line up. Diary both the day the ship leaves.
What to write into your SPA
- Allowed laytime in running hours, at load and at discharge, and whether it is reversible.
- When laytime starts: NOR rules, the notice period (for example six hours), and what happens if the ship arrives before or after the laycan or delivery window.
- Where NOR can be given: customary anchorage, pilot station, WIBON or WIPON, and the readiness conditions such as free pratique and customs.
- What does not count: shifting, ballast and slops, ship's defects, awaiting pilots or tugs, and any half-rate causes.
- The demurrage rate: a stated rate or a clear rule such as the charter party rate, plus who must show the charter party terms if you are not the charterer.
- Which definitions apply: for example BIMCO Laytime Definitions 2013, so words like "running hours" are not argued.
- Claim deadline and documents: how many days, from which event, and which papers must come with the claim.
- The inspector and measurements: whose time sheets and quantity figures count. Our guide to checking an SGS or Intertek report covers the inspector side.
Pricing sits in the same contract, but keep it separate. The pricing clause names the benchmark and window, as our Platts and Argus guide explains; the laytime clause decides who pays for waiting. Neither should be left to "as usual".
Red flags around demurrage in an offer
- A demurrage bill before any ship has loaded, or before you have a signed SPA, a named ship and a NOR.
- Pressure to pay because "the vessel is waiting and demurrage is running" for a ship you never nominated, accepted or saw tender NOR.
- No laytime clause at all in a CIF or DES offer, or laytime described only as "as per charter party" when the seller will not show the relevant terms.
- A ship with no name or IMO number that is somehow already "on demurrage". Check the ship first with our vessel sanctions and AIS checks.
- Demurrage folded into an up-front fee alongside "port charges", "booking fees" or "dip test costs". Real demurrage is worked out after the operation, from documents.
- A statement of facts you cannot match to the ship's tracking history or the terminal's own records.
- A claim with no supporting papers, or papers that arrive only after the deadline in your contract.
Several of these overlap with the patterns in our petroleum trading scams guide. Genuine sellers can explain their laytime terms in a sentence.
A note on sanctions and origin
A waiting ship is still a ship that has to be screened. Russian-origin crude and products, including grades such as ESPO and Urals, are covered by EU, UK and US sanctions, including price-cap rules on shipping, insurance and finance; we describe these grades for information only. A demurrage payment to an owner or charterer on a sanctions list is a sanctions problem in itself. Screen the ship, its owner and manager before you sign. This guide is general information, not legal advice; laytime law differs between legal systems and the cases above are English unless stated.
Common questions
What is the difference between laytime and demurrage? Laytime is the free time allowed to load or discharge. Demurrage is the agreed payment to the shipowner for each period the ship is kept after laytime has run out.
When does laytime start on a tanker? Usually a set number of hours, often six, after a valid notice of readiness is received, or when the ship is all fast in berth if that comes first. Many sale contracts add rules for ships that arrive before or after the agreed window.
Who pays demurrage in an FOB or CIF deal? The charterer pays the shipowner. Under the sale contract, an FOB seller usually pays the buyer for delays at the loading terminal, and a CIF or DES buyer usually pays the seller for delays at the discharge port. Your SPA wording decides.
What does "once on demurrage, always on demurrage" mean? Once laytime has expired, interruptions that would have stopped laytime, such as weekends or bad weather, no longer stop the clock, unless the contract says they do.
How long do I have to claim demurrage? Whatever your contract says. Tanker charters such as BPVOY4 often allow 90 days from completion of discharge with all supporting documents. A sale contract that only refers to the charter party may not carry that deadline over, so set one in the SPA.
Does TradeNexusMarket calculate demurrage? No. Laytime and demurrage are agreed and settled between the parties to the SPA and the charter party. We check company papers and proof of product before a Deal Room opens, and the ship and the companies in the chain are screened against sanctions lists when a deal names a vessel.
How shipping terms are handled on TradeNexusMarket
Posting a requirement or an offer is free. Before a Deal Room opens, a person on our team checks company papers and proof of product, and members are screened against sanctions lists. Contacts stay masked until a match is approved.
Inside the room, stages run in order: signed SPA with the seller of record, inspection, payment instrument, then shipment. The full sequence is in our Deal Room rules, and the steps before the SPA are in our deal process guide. If the cargo moves from shore tank to ship, our TTT, TTO and TTV guide explains how a tank-to-vessel loading differs from a transfer in storage.
Browse requirements for crude oil (including grades such as Murban, Bonny Light, Basrah Medium and WTI Midland), fuel oil, gasoil D2, gasoline and EN590 10ppm diesel, look at the public board, or create a free account to post a requirement.
Post free, trade with checked companies
TradeNexusMarket is a B2B marketplace for EN590, Jet A-1, LPG, LNG, crude oil and other fuels. Posting is free and needs no documents. Contacts stay masked, our team makes the match, and both companies are checked before the Deal Room opens. Commission is charged only on a closed deal.
Related reading
- Guide · Deal documentsIncoterms 2020 for oil cargoes: FOB, CIF, CFR and DAP explained
- Guide · Crude oilLOI, ICPO, SPA, POP: the crude oil deal process in plain English
- Guide · ComplianceVessel sanctions screening and AIS gaps: the ship checks to run before you sign
- Guide · Pricing referencesPlatts and Argus benchmarks explained: CIF NWE, FOB Singapore and FOB Arab Gulf
- Guide · Deal structuresTTT vs TTO vs TTV: how diesel actually changes hands at a terminal
- Guide · Deal documentsHow to verify an SGS or Intertek report with the issuer
- Guide · ShippingQ88 and vessel vetting: how a buyer checks the tanker before accepting it